• Notice for iPhone users: DO NOT use the image size reduction option when uploading photos to the forum. This causes portrait images to post as landscape. We have added a warning to the image insert pop-up as well.

Freedom Steel

Nice flex testor right in front of the shop. Whole thing looks great :thumbsup:

Truck

Hehehe...almost looks like I planned it that way. Now I need more rocks :thumbsup:
Thanks for the compliments, guys. Hopefully all goes well with the inspection today and the overhead door guy finishes up. Electrician is due out on Friday.
 
Doors are done. Got home for lunch right before the inspector left...he flagged it for not having diagonal bracing in the corners and I noticed that they forgot to run a course of screws in the siding just to the left of the 16x12 and need another nail or two in the trim there too, so the builder will be back tomorrow to take care of those items. The electrician should be by tomorrow too.

OB1022aJPG-1.jpg


OB1022bJPG-1.jpg


OB1022cJPG-1.jpg
 
Jeepskate...how hard was it to put the heated floor in? we're about to do a 50x90 here pretty quick and we were going to do it ourselves. any pointers?
 
heres our little project we are doin ourselves

these are pics of our boat shed. its our 3rd shed we have built ourselves for ourselves in the last 1.5 years. the first was a 60x170 for our hay shed, second which isn't quite done is our mechanic shed and its 50x90, now this is our boat shed which is 40x60. All have been built the same way so far. We went with metal cause my whole family knows how to weld and we are not carpenters by any means. I vividly remember welding up perling on the roof at the beginning of June about 25 feet up and boy was it HOTTT. We have one more to go which is another 40x60 and that is for me and my dads many projects which include 1 cj7, 3cj8's, a 76 F-250 4wd with a 428 cobra jet(dads first new truck) and a 1969 Mach I Mustang with a 351 Cleveland(dads high school car)

IMG_0393-1.jpg
IMG_0390-1.jpg
IMG_0392-1.jpg
 
Nice.....Just real nice! Congrats............
 
That is the hotness... :bow:

Thanks. I still can't quite believe everything that's transpired in the past couple of years (some good, some bad) and keep waiting for someone to pinch me. I'm about ready to finally exhale as I scrape together the last few pennies to finish paying for everything (I'm about $7-8k over my original budget). Still plenty to do to finish up the inside, but at least the big stuff is out of the way and the Scrambler can come home. :thumbsup: I try not to look too hard at it when I'm in the back of the warehouse; I'm sure it's got a healthy coating of toner dust on it from the laser printers going through the shredder. I shipped out a bunch of LCD panels this afternoon that I sold (yes, I'm wearing a lot of hats these days to stay employed and keep the company running...commodities other than gold are heading down the drain again) that had been packed for about a week and even those boxes had a fine coating of toner dust on them.
 
Jeepskate...how hard was it to put the heated floor in? we're about to do a 50x90 here pretty quick and we were going to do it ourselves. any pointers?

Plan, plan, and plan some more. There's actually a tube layout program called LoopCAD that you can download a 30 day fully functional demo of which I found nearly indispensable (I made a few field changes to work around where I'll eventually put a 2-post lift). You want O2 barrier PEX-B and try to keep your loops to 250' or less to minimize temperature drop (I've got 760' left from a 1000' spool that I'll give you a good deal on if you're interested). You'll need to insulate under the slab and around the perimeter with 2" thick hi-density XPS foam sheets, cut the tops of your perimeter pieces at 45 degrees. I stapled my PEX to the XPS (bought staples & rented the stapler from Blue Ridge...Google 'em), then the mesh was laid on top of it. Lots of folks lay the mesh/rebar, then attach the PEX to that, but then you never quite know how far down in the slab the PEX is. The concrete guy was very happy to work on mine as he knew exactly where the PEX was and could set his depth without worry when cutting the concrete. I did mine by myself, but an extra set of hands to manhandle the spool of PEX would've been a plus. Definitely have to plan first and figure out your zones (if you're going to have multiple) and number of loops...this will affect what you need manifold and valve-wise. I kept mine simple with a single zone of five loops. Some folks do multiple zones if they're going to divvy up the building into different rooms or extend outside for ice/snow melting. There's some good PDF's to download at radiantec.com

If you want to know anything else, just post up or PM me and I'll do my best to answer you or point you in the right direction for the answer.
 
thank you so much for the info. I'm sure i'll be back asking questions! We have everything to do the floor its just trying to find the time to get started. We have been toying around with having a contractor do it too but they quoted 17k! ouch
 
Recycled some cinder blocks from when we removed some offices at work and made a little pad for in front of the man door (stepping out downhill into mud was getting old), partially trenched for phone, TV & network cabling and ran than and tested it.

OB1108aJPG-1.jpg


Puicked up some 400 watt metal halide canopy lights off Ebay and hung them up in the rafters, mounted the panel and the boxes and prepped for the electrician.

OB1108cJPG-1.jpg


OB1108dJPG-1.jpg


OB1108gJPG-1.jpg


OB1108eJPG-1.jpg


The electrician came out on Friday (I suspect that he didn't get there until almost noon judging by the lack of progress when I came home for lunch) and took care of all of the outside stuff (mast, meter base, ground rods) while his assistant got started on the inside (ran the feeds for the two rear wall circuits and the heating pump). They came back around 10:30 AM on Saturday, buttoned up the outside, ran the circuits for the compressor, the welder, and the other three walls, messed up the circuit for the boiler despite me leaving a note on Friday and then making sure that the assistant understood what he was supposed to do on Saturday. I swear there's something in the water out here...these folks work slowly, can't follow directions, and don't seem to have enough sense to stop and ask questions. He was instructed to take my roll of 8-3, run the welder circuit on the back wall, the boiler circuit next to it, and then use whatever was leftover for another welder circuit on the right wall. Well, he ran 12-2 for the boiler and then ran the second welder circuit with the 8-3 leaving me short for the correct boiler run, so I ended up with the correct boiler circuit further down the wall than I wanted it after I pointed out the screw-up. They said that they'd do my branch circuits even though I said I planned to do them myself later, so I went on and put up the boxes & conduit Friday night, and of course they didn't finish that (only ran one), so I did that myself yesterday in about 45 minutes. The feeds for the lights were run down the wrong conduits, so I have to pull them back and swap them and then run all of the lines to the lights. They also ran one of the light circuits with 14-3 when they were supposed to use the 12-2, so I had to buy more 14-3 this morning and order another 15 amp breaker. I can't complain too much for $600 (I was at least smart enough not to pay the guys by the hour) which was a bargain and they did do a good job overall...very neat & orderly, nothing half-*ssed. I bent and installed the last piece of conduit for the lights last night and prepped the branch circuits so that I can install the receptacles. Probably button those up this evening and get started on the lights.
 
Last edited:
Jeepskate....

On your heated floor what temp is your water heater putting out and what temp does it come back at? We got the concrete poured..sand then plastic then like an aluminum bubble pack then lines with 7 inches of concrete on top of all that. We have a 25 gallon fast recovery water heater that is 75,000btu. We had water going out at 160 and it comes back around 50. How hot can you turn the water going in up to? We don't have the doors installed yet, we just have tarps over all the doors. the air in the shed is 34 degrees. It's suppose to get down to 5 degrees tuesday night. Just needing some info on what we can and cant do.
 
I don't have my heat hooked up yet. Electric should be hooked up tomorrow (engineer was leaving when I got home for lunch today...said the ground was too soft for his truck and that he didn't have a tall enough ladder with him so he'd be back tomorrow with a taller ladder and a helper) and I have to scrape together the money for the boiler and pump (just had to buy new tires for my truck). Doesn't sound like you insulated under your slab properly (nothing you can do about that now)...that bubble stuff doesn't cut it, you need hi-density XPS like the pnk board that I used. As a result, you're dumping a lot of heat down into the ground, so not only do you have to get your slab up to temp, but the ground underneath as well...that's going to take time and probably would've gone better if you'd turned your system on before it got cold. Also, how long did you make your PEX loops and how did you route them? Some people have signifcant temp differences like you, but the routing of the loops prevents any cold-spotting. Big temp drop = more energy con$umption to heat that water back up. If your loops are too long, you'll get those huge temp drops too...again, nothing you can do about that stuff now since it's all set in concrete now. Putting the doors on and insulating the walls & ceiling will all help by reducing your heat loss. 200 degrees is about the limit...should be printed on your tubing, so check that to be sure.
 
the shop is 50x90. We ran 500ft loops. and we routed it every 18" on center. We have the water heater at 180 degrees now but I think we are fighting air in the tubes somewhere. We are doing all this by the seat of our pants. We've done it all ourselves, and we farm so we have to do it ourselves right!? ;). We got put between a rock and a hard place when they started forecasting 5 degree nights. We're also putting a loop around the outside of the building I think. We haven't poured any approaches yet, I don't know what the gain of it will be but we have extra so why not.
 
Those 500' loops are too long...300' is about the max, typically try to stay close to 250'. If you used 1/2" PEX, 12" on center works best for that size tubing. Again, nothing you can do about any of that now. Easy enough to DIY which is what I did, but you have to do the research and the planning before anything is laid. I'm going to guess that you also don't have any perimeter insulation...that's another *huge* heat loss. That's one spot where you can probably make a correction. Insulate around the perimeter of the slab with the HD XPS foam, then do your approaches. That should make a significant difference since most of the heat loss is through the slab perimeter. You'll get *some* payoff on the poor underslab insulation in that the ground will store some heat allowing you to coast through some of the early Spring before the seasonal temps come back up to where the heat isn't needed. Next year, turn that sucker on around October or so before it's really needed so that you can start building up the heat.
 
we got the air out of the system finally and we set the water heater at 180 but now the water is coming in at 40 and going back out at 90. So we basically just started heating now. We used 3/4 inch tubing instead of 1/2". When you talk about insulating the perimeter can you explain a little better on that please?
 
Sounds like the water is pumping through faster than the water heater can heat it up to full temp. There's a calc to figure out how much water is in your PEX...I'll see if I can find it for you. You're probably going to either need a larger hot water heater or a boiler. I think you're probably way undersized with that 25 gallon unit...I've seen guys with smaller shops running bigger tanks than that. I'm assuming you've got a t-stat wired in? You should definitely run a heat loss calc (there are on-line calculators) to see what kind of BTU's you're looking at. For the perimeter insulation, you'll want to dig down around the perimeter so that you can see all 7" of your slab, cut strips of the XPS at about 5" tall, lay them up against the slab and backfill, then pour your approaches. Your tube spacing is fine for the 3/4" PEX, but you definitely flow water through faster with that bigger diameter. The 50 degree drop is definitely better than the 110 drop, so you're probably starting to overcome some of the loss into the ground. Let's see what it's doing in a couple more days before changing anything other than adding the perimeter insulation and putting up the doors.
 
Last edited:
Woo-hoo!! I've got power!! Everything is working just fine so far. Tested the outside lights when I got home, tested the 120V receptacles after dinner (needed to pull the extension cord back up to the house to charge the new battery for the generator), and just came in from testing the receptacles (3-way circuits) for the flourescent lights (have my halogen work lights plugged into the bank near the service door right now), the welder receptacles, and hauled one of the metal halides back up to the rafters and plugged it in. I think it's going to be like daylight in there with all 5 metal halides running. Once I hang the rest of the lights, I'll schedule the final inspection.
 
Congrats!!! It is great to finally have electricity and pull the extension cord from the house...I loved that feeling.

Truck
 
Thanks. Couple of pics from Saturday night:

OB1212aJPG-1.jpg


OB1212bJPG-1.jpg


Installed the multi-tap setup in the 5th light a couple of nights ago, just waiting on the bulbs and socket from the Ebay guy now so that I can hang the last two (should have them this week).
 
Lights

I bought a place by Zillah, Wa. and it came with an equipment shed. Basically a pole building like yours with the front open. It's 900 sq. ft. This summer I am going to add the other half to finish it to 1,500 sq. ft. enclosed with three roll up doors. I like your lights. I saw where you got them on E-Bay. Would they have any more? Please let me know your source and just what kind of lights they are. Do you have any idea how many I would need?

Thank you in advance.

Captain Jack Smith, Pastor
The Salvation Army
Juneau, Alaska
 
Back
Top