Your comments are appreciated, Tom. I honestly probably would've split the cost with him had I not lost the $1500 on the steel building through his failure to get an estimate from the concrete guy when I was making my decision back in May/June. He made assumptions rather than make a phone call and that is basically the same thing that happened here with the electrical. Simple fact is that at this point, I flat out do not have the cash to spend any more on this...hence no lift, no driveway, no insulation, no interior walls, no heat. It's my nature to compromise even if I don't feel that I'm at fault as I do not like conflict...I simply don't have the cash to compromise...I barely have enough left to finish paying for this.
I did not step into this with the intention of becoming as involved as I did. The builder simply laid these things (permits & drawings) off on me. We were sitting at the table one evening when he brought the first contract over and HE asked ME what was required for the permits and I grabbed my laptop and pulled the checklist up for him and he starts asking me what some of the things are. I thought I was just helping the guy out since he's busy and doesn't really have the time to sit down and do drawings and apparently doesn't use the internet which is where I got all of the forms & checklists...there I go being nice & compromising

Yes, I picked the spot based upon setbacks and the lay of the land, but I'm not a contractor. He was right there with me and whipped out his tape measure and started marking the corners and looked up and saw those power lines and:
1) Thought the building would clear (didn't measure).
2) Didn't know about AEP's easement (and didn't bother to call them)
3) Didn't know about the OSHA regulations (and later put himself & his crew in danger...again, a phone call to AEP would have netted him this info)
4) Assumed it was my service line despite the fact that the transformer is on the pole in the woods across from the building and the service line runs underground to the house from there (he was going to touch those lines if the electrician hadn't come by and stopped him).
5) Kept building to the point of no return when it should have been pretty obvious that there was going to be a clearance problem since he had all of the materials & measurements. He had 5 of the 6 back posts set the first day and at that point he could've checked his clearance and we could've backed up at that point and simply pivotted the building or moved it 8 feet further forward. He waited until the walls were completely framed and most of the fill was in place.
He had no problem using his knowledge to change other things like moving my service door from the front wall to the side wall so that there'd be more rigidity on the front wall, having me bring the vertical slab insulation up to the finish level of the floor so that the concrete wouldn't crack, opinions on the potential build sites, etc. This was simply a case of the man not knowing something that he should've known (and thereby putting himself and his crew at risk) and making faulty assumptions that would've been cleared up in the first 60 seconds of talking to an AEP engineer.
The only thing that I actually signed on to do here was the slab insulation & PEX which he didn't know how to do and even there he weaseled out of doing the vapor barrier and didn't finish the fill/grade job...I spent two hours out there when I should've been working on the insulation finishing up that job ("What area wasn't done? Well, there's a couple of piles of gravel left there...") because he quit early when he realized that he couldn't set the trusses.
Definitely a lesson learned. If I ever have to do something like this again, I'll either make sure that I'm dealing with someone like you, or I'll walk into it assuming the role of general contractor and make sure that I do all of the research.