Been awhile since any progress with the shop addition.
Maybe a little burn out, sickness and other projects got in the way, just life in general.
But we are back on it now.
Lots of wiring and hanging OSB
Mini Split's installation. Can't get them going fast enough, we've been in a heck of a heat wave in SE Kansas.
Money well spent for these head unit install brackets.
Since we had 2 x 6 walls, decided to run our lines sets, drain hose and control wires in the wall.
Makes for a much nicer install not seeing that on the outside of the building.

Both head units installed.

Got vacuum pulled on one unit, all that's left on it is to hook main wire to breaker box.
Hopefully a couple evenings will have the other one ready to go.