Freedom Steel

Things are still plodding along. I ordered the building framed for a 16x12 on the front and 9x7 on the side but bought the doors locally as their installed price was only marginally higher than the door price from Clopay via Freedom Steel. Decided to hold off on replacing the house doors until after the building is up just in case I need that additional cash. I'll frame out and install the service door later myself. The PEX and supplies are sitting in my garage, just need to buy staples and rent a stapler when the time comes. The plans arrived Friday evening, so this week's mission is to get cracking on the permits. Builder called this morning (he came in with a reasonable number) to see if the plans arrived so he can schedule breaking ground. If things go okay, I'll hopefully be breaking ground in a week or two to grade and pour the footers.
 
Talked to the county building dept. and found out that I need a zoning permit from the township (there's no formal 'seat' for the township, just 3 elected trustees and a zoning inspector who are retired guys 'working' from home). Just got a call back from the inspector and found out that I have to be 25' off of the property line which nixes my build site close to the house. Can't go behind the house because my leach field is back there plus I'd have to be 50' off of the property line. So, looks like we're going back over in the clearing across from the electric pole or the clearing uphill from there where I originally thought I might build, separate meter, no driveway unless the grading & gravel is cheap, and a shed close to the house. Gonna have to change my door layout now too.
 
In my area, a varriance can be granted if the adjoining property owner has no objection. You might ask if something like that is possible.
 
I am glad there is no zoning where I live...i am 10' from the property line with my shop..I dont know who you are getting your doors from..but i only paid less than 2k apeice for my 18x10 doors and they are 1-3/8 commercial insulated doors!!!
 
They only do variances here if there are unique circumstances to the property that make compliance a problem *and* compliance would cause undue hardship...both cases must apply. Now the next county over, anything goes.
 
Un-freakin-real!! Because I have a 'flag' lot (the shape), the code for me is different...I have to be 75' from all property lines which means I have to try to get a variance. Inspector is coming out tomorrow to officially reject my permit so that it can go to the appeals board, I have to supply the names & addresses for all of my neighbors including the ones across the street, pay $125, and wait for a public hearing.
 
Phew...okay, I think the crisis is over. We went back out with the big tape measure and worked our way in from the street based on the survey and the lot line at the 'flag' is about 30' closer to the street than we had been told by the PO. I can come in about 100' from there into the clearing, avoid cutting down the apple trees and leave the pathway open to the uphill clearing. I'll draw it up tonight and call the inspector in the morning and hopefully have my zoning permit tomorrow evening, and call Freedom Steel to have them move the 16x12 door.
 
Busy day of phone calls & e-mails. Updated the builder, he'll be out tomorrow evening to look over the site and make the necessary adjustments. Contacted the electric co. and am waiting on a call back from an estimator to find out how much if anything the install is going to cost me as well as what the monthly hit is going to be and what rate they're going to charge me on usage. Called the garage door guy about adding a panel to the 9x7 to take it to 9x9. Let the electrician know what was going on and finally contacted Freedom about the door change. They want $900 to draw up new plans (I know AutoCAD, it's about 30 minutes worth of cutting/copying & pasting) so I'm trying to work a deal on that...I know I should pay since I'm changing things, but almost $1k is insane, plus they put the wrong address on the plans (used my work/delivery address instead of my home address). The zoning inspector came by this evening and $36 later I have that permit in hand. We had the plot from the survey when we bought the house, so I just made copies of that and added the outbuilding to it with the setback measurements.
 
Still making good progress. I got my soil & water exemption from the county (cover up over 3,000 sq ft with your building & driveway combined and you have to jump through hoops and pay money...I'd be there if I'd been able to build on top of the hill) then strolled down the hallway and turned in everything for my building permit...should have an answer back within 5 business days. The builder is on vacation next week, so if all goes well, I'll have the permit when he gets back and we'll break ground to dig the footers and get the holes inspected before pouring. I spoke with the president at Freedom and we worked it out that the redraw with the 16x12 moved and 9x7 upsized to 9x9 will cost me $300-500 which I can live with. The garage door guy will order the extra panel, longer track & heavier springs on Monday. I'll probably buy the pink board for insulating the slab next week while Menards has it on sale and just store it at work until time to lay it out and run the PEX.
 
Sounds like you are making progress. I know it is slow, I've been there.

Truck
 
Hopefully this will be a good week without any surprises. I have a feeling I've got a surprise waiting once the excavation begins since this used to be a farm, drain tile is common, and I'm on a slope leading toward the drainage/run-off creek that runs through our woods.

Updated overhead pic:

GEHome-1.jpg
 
Still no word from AEP on how they're going to charge me for the meter & usage...must be nice to be able to blow off customers for a week and a half, I'm in the wrong line of work ;) The engineer did call me back and he verified that they'd just run overhead, no charge, and the building is tall enough that I don't need a mast. Hoping to hear back on the building permit today or Monday. Got a couple of Linksys WRT54G's from work and started flashing them with DD-WRT so that I can convert one into a repeater and the other into either a bridge or a repeater-bridge in order to extend my wi-fi coverage out to the building. I'll probably need to pickup a couple of outdoor antennas too.
 
Maybe you should look at the Pringle can antenna's They are very directional and could serve to pump signal from the house to the garage in line of sight.


Carl
 
I had forgotten about the can-tennas. I can get to the edge of the clearing and still have usable signal from my access point which is in a closet under the stairs about midway between the front & back of the house. I'm going to try the repeater upstairs in each of the front rooms and see where I get the strongest signal...I have a feeling my bedroom will work best since it'll be the least obstructed by the trees. If it isn't string enough/the trees are too much of a problem, I'll probably put it in the 'attic' and mount an antenna by the chimney where I left the pole from the old TV antenna.
 
The hi-density pink board for the slab insulation is purchased. They had plenty in stock, so I didn't have to pick it up on the spot. The builder got back from vacation Saturday and had a message from the plan reviewer...they want cross-sections of the footers & slab, so he's supposed to come out this evening and measure everything up and calculate the amount of fill so that we can submit those two drawings. Hopefully this week is a good week.
 
Aaaaaargh!!! I'm feeling like stabbing something again. Almost got into an argument with the builder when he called this morning with the concrete quote...$16k!!! Then had the nerve to tell me "See, I told you steel buildings were more expensive than pole buildings..." I almost snapped, but I bit my tongue and calmly replied "No, the steel building was cheaper, it's the concrete that's more expensive. You should have talked to the concrete guy back when I was making my decision on which building to go with. I was working from the $5-6k that you broke out of the pole building quote (which he's now saying will be more like $7k if I get the variance, $9k if I don't) over the phone and I even asked you if that cost would stay the same." No response. He's an excellent builder by all accounts, but he needs to do his darn leg work up front. Both the location and the foundation could've and should've been sorted out back in May/early June and all it would've taken was a couple of phone calls. Now I'm checking to see what it's going to cost me to back out of the steel building contract...
 
Sorry to hear the setback. Remember my thread? My concrete is still the most expensive thing in the building. Slab cost me $15kish & I wasn't happy about it. I was expecting $7k. That is why it took me a year to save up just for the slab of course by the time I saved the money the cost went up another $2k!!!

Truck
 
Call Around.

There should be a lot of Conc. guys out there that really need the work and willing to do it for less.

Those prices sound really high. But it does depend on how much steel and how deep you have to go with the footings.


Carl
 
Now that you mention it, I do remember that, Truck. I talked to the concrete guy today and he said that there's a couple of options that can shave the price down, like pouring the footers with a pad on the top and doing block retaining walls in between or a shorter poured wall (I think he spec'd it out with the footers dug as trenches), and I can skip the slab for now and do that later. Footers have to be 3' deep. About $3k of it is material & labor from the builder for the fill (using some kind of stone & powder mix that is wetted and tamped in place in layers...supposed to hold almost like concrete so that it doesn't shift and push against the walls). Might be worth it to just have regular fill brought in since it'll have time to pack in before I have the money for the floor. I should know what's up with backing out of the steel building tomorrow, then I can make a more informed decision.
 