Well I am glad my comments were taken in stride. I didn't want to stir anything up. It sounds like your contractor is one of those "old school" guys that doesn't want to learn any new tricks, or follow any regulations that might get in the way of how he has been doing things for the past 20 years. I am sure your building is going to turn out great.
 
No worries, Tom. I appreciate your insight into it from a contractor's point of view. I would definitely be more open to splitting the costs with him if I had walked into this acting as the general contractor. I essentially fell into that role somewhat due to him not doing research, etc or stepping up to handle things. I would call to ask him something that he would have to ask one of the subs and he would just give me their phone number. The one time that he did make a call on my behalf, he screwed things up and made the electrician think that I was trying to cut him out of the job whilst pumping him for info on what materials to buy (just wanted the specs so that I could try to find a good deal on them). I'd say that your assessment is correct...old school guy who doesn't want to learn anything new. He actually did a partial roof & truss replacement on our retail building and had to go back and put hurricane clips in because he had done some old-school thing instead and the inspector failed it...cheaper to just keep up with what's going on than to have to go back and undo/re-do things. I'm sure that I'll be happy once it's done and I think most if not all of the BS is behind me...just gotta call AEP and find out why I don't have the papers to approve the new easement yet.
 
Spoke with the AEP engineer and I'm on the schedule for next week to have the new pole set and the lines moved, so the building should probably be 'done' (I'll still need to insulate, put in interior walls & a ceiling and finish the heating system as finances & time permit) the following week.
 
Pole was set this afternoon, hopefully the line crew will be here tomorrow to swing the lines over.
 
Went home for lunch and the line crew had just finished up, so the lines are now moved and we're ready to get going again. Just waiting for a call back from the builder to let me know when he's going to get started.

OB1005aJPG-1.jpg


OB1005bJPG-1.jpg
 
Last edited:
A little better than half the roof is done. The builder said they'd finish it tomorrow and would have 1 or 2 walls done as well and that I should have the garage door folks come out on Friday. He expects to be done on Friday barring any weather delays. I moved the PEX out of the way of the siding and brought the service door down from the attached garage (bought a door on sale at Menards on Sunday) when I got home from work. I'm going to see if he can pick up the owner's Gradall after the weekend so that I can use it to move all of my crap down from the house (have to bring home a few pallets from work)...not looking forward to humping half of it back up from the basement. I'll probably bring some pallet racking home this weekend as well.

OB1013aJPG-1.jpg


OB1013bJPG-1.jpg


OB1013cJPG-1.jpg
 
Darn...rained out and probably won't be clear until Monday. Went home at lunch time and they had packed it in. They had to add another row of PTL board around the bottom and they got most of the north wall of siding up before they quit.
 
The rain is holding off so far today. I just got back from lunch and they had the roof done except for the ridge vent and were about halfway done with the siding on the south wall. They should be done with the south wall shortly, and they'll set the header for the 16x12 before they leave. I'm thinking they should have enough time to knock out at least one more wall. Getting ready to call the garage door guys to tell them to come on out.

OB1016aJPG-1.jpg


OB1016bJPG-1.jpg
 
Last edited:
Contract is finally signed and the builder has his second payment. I cut down a few small trees that would've interfered with the power lines to the building or would've grown over to touch the building/fallen on the building in a good storm. Brought home some skids & shrink wrap from work and skidded up a bunch of the boxes that were in the garage and down in the basement and ran them down to the building with the Gradall along with a couple of parts cabinets and other stuff that was on wheels. Builder expects to be done on Tuesday and have it inspected on Thursday.
 
Hoped the builder would be a little further along, but he was short two guys. All but the last bit of interrnal bracing for the trusses is done, most of the front siding is done, and all of the front trim is done. He said it may run over into Wednesday, but I think he should be done tomorrow (Tuesday). Overhead doors will be installed later in the week. I'll probably move the next skid that I loaded up down tomorrow evening and load up one more skid to move.

OB1018aJPG-1.jpg


OB1018bJPG-1.jpg


OB1018cJPG-1.jpg
 
They were supposed to be done today, but it looks like they've got about a half day's worth of work for tomorrow (watch them take all day):

OB1020aJPG-1.jpg


OB1020bJPG-1.jpg


OB1020cJPG-1.jpg
 
Got home at lunch time and they were starting to clean up & load up while one guy worked on the roof vent...he was finishing up just as I left to head back to work and the overhead door guy pulled up, so I should have doors when I get home this evening.
 
The overhead door guy only put in about an hour and a half. I moved my M100 down and a few other boxes, tools & odds & ends while I had the Gradall. My wife is happy to have her bay in the garage back and no Jeep stuff in the driveway.